翻訳と辞書
Words near each other
・ Levuka
・ Levuka Airfield
・ Levuka F.C.
・ Levuka language
・ Levulan
・ Levulinic acid
・ Levunovo
・ Levy
・ Levy & Klein
・ Levy (surname)
・ Levy Adcock
・ Levy Barent Cohen
・ Levy baronets
・ Levy Chapel
・ Levy County Courthouse
Levy County Nuclear Power Plant
・ Levy County, Florida
・ Levy Economics Institute
・ Levy en Masse Act 1803
・ Levy Gerzberg
・ Levy House
・ Levy House (Reno, Nevada)
・ Levy Island
・ Levy Jewish Chapel
・ Levy Lee Simon
・ Levy Li
・ Levy Matebo Omari
・ Levy Mayer
・ Levy Middlebrooks
・ Levy Mokgothu


Dictionary Lists
翻訳と辞書 辞書検索 [ 開発暫定版 ]
スポンサード リンク

Levy County Nuclear Power Plant : ウィキペディア英語版
Levy County Nuclear Power Plant

The Levy County Nuclear Power Plant is a proposed nuclear power plant in Levy County, Florida. Progress Energy Florida originally estimated that the reactors would cost $5 billion and would commence operation in 2016. But it has become clear that the new Levy County reactors will not start operating for at least another decade, if ever.〔〔
Since Progress filed its application for the new plant in 2008 demand for electricity has been growing very slowly, and natural gas prices are now very low. The utility now estimates that the reactors will cost between $17 billion and $22 billion, not counting financing charges and cost overruns. According to economist Mark Cooper, opposition to the project has mounted, threatening a rerun of the 1970s and 1980s, when the majority of nuclear construction plans were canceled or abandoned.
On August 1, 2013, Duke Energy terminated the engineering, procurement and construction (EPC) agreement for the Levy nuclear project, as part of a settlement with Florida consumer advocates.
==History==
The Levy County Nuclear Power Plant is the umbrella term for a proposed nuclear power plant in Levy County, Florida. Proposed in 2006, Progress Energy Florida (PEF) announced the selection of in southern Levy County for the potential construction of nuclear reactors. The site's proximity to the company's existing Crystal River 3 Nuclear Power Plant was expected to provide opportunities for efficiencies in shared support functions at both facilities. However, Progress Energy (at this point, a subsidiary of Duke Energy) announced the decommissioning of the Crystal River reactor in February 2013 after cracks formed in its containment dome, estimated at $1.5 billion to repair. The company made no reference to constructing any new nuclear facilities in the region, only stating that they are "evaluating a number of potential sites for new plant capacity that may be needed in the future to meet Florida customer needs."〔(【引用サイトリンク】title=Crystal River Nuclear Plant to be retired; company evaluating sites for potential new gas-fueled generation )
Progress Energy Florida submitted a filing with the Florida Public Service Commission (PSC) on March 11, 2008, outlining its need for additional electricity and proposing to meet that need with two nuclear units in Levy County. The PSC scheduled hearings on the project in late May, and approved it in July.
The company then applied for a Combined Construction and Operating License (COL) from the Nuclear Regulatory Commission (NRC) on July 30, 2008. Costs of the power plant are estimated at $19–24 billion, including $3 billion for necessary transmission upgrades. The first reactor is expected to come online in 2024 and the second one 18 months later.〔

On October 14, 2008, the PSC voted to allow PEF to charge customers an additional $11.42 per 1,000 kW·h, beginning in January 2009, to pay for the Levy plant and work upgrading the Crystal River plant.〔
〕〔

On January 5, 2009, PEF awarded an engineering, procurement, and construction (EPC) contract to Westinghouse and The Shaw Group's nuclear division to build the two reactors for $7.65 billion. The reactors were supposed to be operational by 2016–18.〔
〕〔

In May, after the NRC denied permission to begin excavation work on the site to prepare for construction prior to issuing the COL, Progress Energy announced that commercial operation of the two new reactors had been pushed back "a minimum of 20 months."
In view of the delay, Progress Energy has requested approval from the Public Service Commission to reduce the project cost to consumers in 2010 from $12.63 to $6.69 per 1000 kW·h.〔

On August 11, 2009, Florida governor Charlie Crist and his cabinet unanimously adopted the recommendation of the state Department of Environmental Protection, and approved the plant's Site Certification Application (SCA). Site certification is the last major state-level approval needed before Progress can start constructing the Levy plant. The approval included a requirement that Progress shut down coal-fired electrical generating units 1 & 2 at its nearby Crystal River Energy Complex by the end of 2020, assuming the timely licensing and construction of the Levy nuclear power plant.
On August 1, 2013 as part of a comprehensive settlement with a group representing Florida consumers Duke Energy announced termination of the engineering, procurement and construction (EPC) agreement for the Levy nuclear project and consideration of a natural gas-fueled alternative but said it would continue to seek a combined construction and operating license (COL) for the project from the Nuclear Regulatory Commission (NRC). A final decision will be made in the future based on "energy needs, project costs, carbon regulation, natural gas prices, existing or future legislative provisions for cost recovery, and the requirements of the NRC’s COL" and other factors.〔 Research published in May 2013 by ''The Tampa Bay Times'' showed that a plant fueled by natural gas was nearly certain to be cheaper than a nuclear-fueled plant over the next 6 decades. About $1 billion had been spent on the preparatory work for the Levy nuclear project.

抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)
ウィキペディアで「Levy County Nuclear Power Plant」の詳細全文を読む



スポンサード リンク
翻訳と辞書 : 翻訳のためのインターネットリソース

Copyright(C) kotoba.ne.jp 1997-2016. All Rights Reserved.